WORK PROGRESS ON FAILED SLOPE , RESIDENTS MEET

18thMAR10 -1. Follow up with HCM, MICROPILLING is in progress and 25pts completed. Total 285pts required for this task. Some technical problems encountered but can be ovecomed. Site work is going on till 10pm daily to meet date line. 2. Last week HCM had meeting with responsible authorities-MPAJ, SYABAS, INDAH WATER and TNB. I have been liaising constantly with MPAJ and HCM to address issues at hand. 3. WANGSA9 RESIDENTS MEETING will be on saturday 3rd April at Hillside Corner Rest 8PM. Your attendance is greatly appreciated. Tq n Rgds, yenhee