Meeting with HCM and sub contractor this morning 10am has concluded that soil nailing is near completion, 15 percent of work left. Estimated to be completed just before CNY ie mid February. Micropilling will commence then but they are facing a hiccup of storage and place for machinery which has indirectly affecting the work progress. Mr Yap and myself have been working on this for the last one week. Micropilling will take 4 months base on 12 hrs daily. HCM indicated the whole project will complete in OCTOBER.
Thank you and regards,
YENHEE