Thursday, January 14, 2010

Update: Meeting with MPAJ IR Hj Zolkeflee

With reference to the above, my first meeting with Ir Zol went well. Ir Zol who has succeeded En. Othman Idris has been briefed in details on the 10 issues proposed. (letter is attached) MPAJ will act and reply accordingly in black and white. Will follow up and post replies in my blog.
Thank you and regards,
YENHEE
The above post was sent via SMS

Wednesday, January 13, 2010

Letter to MPAJ - follow up

Ir Hj Zolkeflee bin Abd Hamid
Majlis Perbandaran Ampang Jaya
Jabatan Kejuruteraan,
Aras 11, Jalan Pandan Utama, Panda Indah
Selangor Darul Ehsan
55100 Kuala Lumpur 13th JANUARY 2010

Dear Ir Hj Zolkeflee,

Ref.: Follow Up of Issues Proposed by Residents of Wangsa 9, Bkt. Antarabangsa

With reference to our tele-conversation on Tuesday (12th January 2010), these are the following issues the residents would like to propose. These issues have prior been highlighted to the attention of Encik Othman bin Idris on 28th October 2009. We take this opportunity to thank you on a cordial meeting we had with your department on the 28th October 2009, with the presence of Puan Noor Azaliah binti Hassan, Encik Rojohar Salleh and Encik Amran Ismail (Jabatan Perbandaran). Encik Othman has now been transferred to MPS, we hope you will be able to continually support our requests as listed below:

  1. To represent us as an official communication channel to liaise with all related authorities in particular JKR.
  2. We would like to know a definite date for evacuees to go back to their homes.
    The respective designs on the failed slope by JKR.
  3. Security – some immediate measures need to be looked into seriously since there has been several breaking-ins. The last one just occurred on the first week of January this year. All water meters on Jalan Wangsa 9 have also been stolen as on the 2nd of January 2010. All evacuees are very concerned with their properties being invaded by strangers.
  4. Waver of quit rent and land assessment for the year 2010.
  5. Lightings on Jalan Wangsa 9 – spots lights which were installed previously, only two are working. If more lights are installed, the place will be lit up better hence will deter intruders from taking opportunities on the abandoned houses.
  6. Temporary supply of water and electricity for general upkeeping since the house has been abandoned for more than one year.
  7. Recompact and repave the new road for the other half of Jalan Wangsa 9 (further proposal on this will be written in to your attention again).
  8. Proposal of underground cables – please refer to the letter dated 21st Oct 2009 as attached.
  9. Landscaping of proper fencing and trees that needed to be pruned once the properties ready for habitation.

I look forward to meeting you tomorrow (14th January 2010) in your office to discuss further on the issues above.

Thank you.

Yours faithfully,

YENHEE
Committee Member & Spokeswoman for Wangsa 9

Tuesday, January 12, 2010

UPDATE- Progress of Work on Failed Slope

Meeting with HCM and sub contractor this morning 10am has concluded that soil nailing is near completion, 15 percent of work left. Estimated to be completed just before CNY ie mid February. Micropilling will commence then but they are facing a hiccup of storage and place for machinery which has indirectly affecting the work progress. Mr Yap and myself have been working on this for the last one week. Micropilling will take 4 months base on 12 hrs daily. HCM indicated the whole project will complete in OCTOBER.

Thank you and regards,
YENHEE
The above post was sent via SMS

Sunday, January 10, 2010

JAN 2010 Rental Subsidy

Kindly be informed that this month's subsidy will be delayed. This is because MPAJ is in the process of closing its 2009 account.
Thank you and regards,
YENHEE